HCL Workload Automation, Version 9.4

For IBM Workload Scheduler for z/OS jobs

The syntax is:
appl  [IA(yymmddhhmm)|IATIME(hhmm)] [...]
     [DEADLINE(yymmddhhmm)|DEADLINETIME(hhmm)]
     [PRIORITY(pri)] 
     [CPDEPR(Y|N|P|S)] 
where:
appl
The name of the IBM Workload Scheduler for z/OS application to be inserted into the current plan.
IA
The input arrival date and time in the form: yymmddhhmm.
IATIME
The input arrival time in the form: hhmm.
DEADLINE
The deadline arrival date and time in the form: yymmddhhmm.
DEADLINETIME
The deadline arrival time in the form: hhmm.
PRIORITY
The priority (1-9) at which to run the application.
CPDEPR
The current plan dependency resolution selection.
Y
Add all successor and predecessor dependencies.
N
Do not add any dependencies, (the default.)
P
Add predecessor dependencies.
S
Add successor dependencies.

For complete descriptions of the parameters, refer to the IBM Workload Scheduler for z/OS documentation.