HCL Workload Automation, Version 9.4

Scenario 1: Creating the production plan and viewing its contents

The scenario shows you how to:
  • Create and extend a production plan
  • Understand if a plan was created successfully
  • View the contents of a plan
The scenario performs the following actions:
  • Creates a production plan with a duration of 24 hours
  • Inserts into the plan all the jobs and job streams that the tutorial already added in the database with their dependencies
  • Views the contents of the plan
Commands used in the scenario in their run sequence:
  1. JnextPlan
  2. conman sc (showcpus)
  3. planman showinfo
  4. conman ss @#SMPL@ (showschedules)