carryforward
Makes a job stream eligible to be carried forward to the next production plan if it is not completed before the end of the current production plan.
Syntax
carryforward
Examples
The following job stream is carried forward if its jobs have not completed before preproduction processing begins for a new production time frame.
schedule sked43 on th
carryforward
:
job12
job13
job13a
end