Starting production plan processing
About this task
- Log in as TWS_user on the master domain manager.
- At a command prompt, run the script command . ./TWS_home/tws_env.sh in UNIX or TWS_home\tws_env.cmd in Windows to set up the environment, then run
the JnextPlan job by entering, for example on a UNIX workstation,
the following command:
JnextPlan.sh -from 05/03/06 0400 tz Europe/Rome -to 06/06/06
This creates a new production plan that starts on the third of May 2006 at 4:00 a.m. (Europe/Rome time) and stops on the sixth of June 2006 at 3:59 a.m. The processing day will start at the time specified on the master domain manager in the variable startOfDay.
- When the JnextPlan job completes, check the status
of HCL Workload Automation:
If HCL Workload Automation started correctly, the status isconman status
Batchman=LIVES
If mailman is still running a process on the remote workstation, you might see that the remote workstation does not initialize immediately. This happens because the workstation needs to complete any ongoing activities involving the mailman process before re-initializing. After the interval defined in the mm retry link parameter set in the TWS_home/localopts configuration file elapses, the domain manager tries again to initialize the workstation. As soon as the ongoing activities complete, the activities for the next day are initialized. For information about the localopts configuration file, refer to HCL Workload Automation Administration Guide.
- Increase the limit to allow jobs to run. The default job limit
after installation is zero. This means no jobs will run.
conman "limit;10"