HCL Workload Automation, Version 9.4

Monitoring a cross dependency resolution in the production plan

Shadow jobs are added to the plan as follows:
  • At run time if either of the following situations occurs:
    • A shadow job definition is submitted using the sbj command.
    • A job stream containing a shadow job definition is submitted using the sbs command.
      Note: When submitting a shadow job, specify a destination job stream with a known scheduled time to better control the remote job instance that will be bound.
  • When the preproduction plan is extended or created and its time frame includes the shadow job scheduled time.
When a shadow job instance is added to the plan, you can start monitoring its status.