HCL Workload Automation, Version 9.4

Scenario 9 part 2: Using variable tables to run different commands on different days

This part shows how you use variable tables to have the same job stream containing two run cycles to launch two commands based on variable substitution. It create a job stream containing a job definition and two different run cycles that address two different variable tables. The scenario performs the following steps:
  • Creates two variable tables and defines variables inside them.
  • Uses variables inside jobs.
  • Defines a job stream.
  • Associates a different variable table to each run cycle.